OTD recovery

Implementation of:

  • A system of steering by the date requested by the customer, a system of forecasts with the participation of the customers and an S&OP process,
  • Buffers of machined and purchased parts, controlled through Kanban,
  • Numerous nomenclatures and task lists corrections,
  • Digital visual management to better manage the workshops,
  • Introduction of buffers and steering after 1 month,
  • Indicator of the number of consecutive days without delay: 148 days reached,
  • Average OTD over the first 12 months: 98%,
  • Successful deployment on 2 other product lines.